The Information Systems Office of the City of Pittsburgh, is soliciting proposals from qualified firms for Internet Access for the City of Pittsburgh. Please submit a proposal which responds to the materials outlined in the attachment. If you are interested, the deadline for submission of written proposals is 5:00 p.m. on Friday, July 12, 1996.

Any questions which you may have concerning the request for proposals should be addressed to:

Howard A. Stern, Assistant Director

City Information Systems Office
City of Pittsburgh
Public Safety Building, 4th Floor
100 Grant Street
Pittsburgh, PA 15219
(412) 255-2152
(412) 255-2355 - fax

Any questions which you may have concerning the technical specifications of the proposal should be addressed to:

Dennis Moul, Unix Network Administrator
City Information Systems Office
City of Pittsburgh
Public Safety Building, 4th Floor
100 Grant Street
Pittsburgh, PA 15219
(412) 255-2167
(412) 255-2355 (fax)
d m m (at) c i t y - n e t (dot) c o m (Internet E-Mail)
http://www.city-net.com/~dmm (WWW)

Thank you for your consideration, and we look forward to hearing from you.

Sincerely yours,


Steven J. Schmitt

Director


INTERNET ACCESS FOR THE CITY OF PITTSBURGH

Request for Proposal

TABLE OF CONTENTS

1.0  GENERAL

1.1  Purpose
1.2  General Scope of Proposed Services

2.0  BACKGROUND
2.1  City Information Systems

3.0  "INTERNET ACCESS" REQUIREMENTS AND SPECIFICATIONS

3.1  General Requirements and Specifications
3.2  Connectivity Architecture
3.2.1  Component I - T1 Service
3.2.2  Component II - T1 Leased Line to ISP Point of Presence
3.2.3  Component III - (2) CISCO Routers
3.2.4  Component IV - (2) Sun Ultra 1 Workstations
3.2.5  Component V - Solstice Firewall-1 Software

4.0  RFP RESPONSES

5.0  VENDOR QUALIFICATIONS

6.0  INSTALLATION AND TRAINING SERVICES

6.1  Installation and Training Services
6.2  Documentation Available at Time of Installation
6.3  Delivery and Payment
6.4  Training
6.5  Maintenance and Customer Support Services

7.0  CONTRACTUAL CONDITIONS

7.1  Rights of Assignment
7.2  Financial Terms and Conditions
7.3  Contractual Terms and Conditions
7.4  Guarantee of Functionality
7.5  Insurance
7.6  Worker's Compensation
7.7  Indemnity
7.8  Patent Indemnity
7.9  Third Party Liability

8.0  AFFIRMATIVE ACTION AND ANTI-DISCRIMINATION

8.1  Minority and Women's Business Enterprise Participation
8.2  Anti-Discrimination
8.3  Debarment
8.4  Statement of Affiliation

9.0  RESPONSE, EVALUATION AND SELECTION PROCEDURES
	
9.1  Proposal Format and Contents
9.2  Modifications
9.3  Cost Estimates
9.4  Vendor Qualifications and Selection Criteria
9.5  Selection Criteria
9.6  Selection Procedure
9.7  Selection Schedule
9.8  Choice of Features
9.9  Right to Change Process, Terms and Conditions, Specifications, Criteria for Selection and                                                   
        Reject Bids


1.0 GENERAL

1.1 PURPOSE

The purpose of this Request For Proposals (RFP) is to provide secure, high-speed, transparent, dedicated access to the Internet from any TCP/IP device on the City of Pittsburgh's internal Local Area Network.

1.2 GENERAL SCOPE OF PROPOSED SERVICES

City Information Systems (CIS) has undertaken a systematic program to provide Internet resources to City employees, and to develop the infrastructure needed to provide traditional services to City residents and businesses via the Internet. By this RFP CIS is seeking to obtain an environment with which it can A) provide high quality Electronic Mail and World Wide Web services to City employees, enabling access to information and communications that can help them better perform their job functions; and B) develop and deploy Internet services to improve the communication between City residents/businesses and the various departments in the City.

2.0 BACKGROUND

2.1 CITY INFORMATION SYSTEMS

The Office of City Information (CIS) is responsible for the planning, acquisition, installation and support of the City's proprietary and open computing environment. Additionally, CIS performs systems analyses, researches industry offerings, develops applications, trains users and serves as systems integrators to departments for solutions concerning their data processing and information management needs.

3.0 "INTERNET ACCESS" REQUIREMENTS AND SPECIFICATIONS

3.1 GENERAL REQUIREMENTS AND SPECIFICATIONS

"Internet Access" is defined in this context as the routing of packets between the City's internal network and the Internet, along with the support infrastructure to perform this task in a secure and efficient manner. It explicitly does not include higher level services such an World Wide Web servers, electronic mail, File Transfer Protocol (FTP), interactive login (Telnet), and shell accounts for users. This RFP addresses primarily the lower three layers of the seven-layer OSI model (Physical, Data Link, and Network). Implementation of the architecture described in this proposal will enable the City to provide of its own accord the higher level services described above.

The City's internal Local Area Network is composed of Intel based PC's and servers, Unix workstations, and a few specialized mainframe interconnect devices. There are a total of approximately 1,200 nodes. It is assumed that the number of internal hosts will grow by at least 25% per year, and the system should be able to support the growth of the next two years without requiring any upgrades. Thus, the connectivity architecture needs to be able to support at least 1,800 TCP/IP hosts on the internal network.



3.2 CONNECTIVITY ARCHITECTURE - 5 COMPONENTS

The connectivity architecture is divided into five separate functional components. They are as follows:

Component I T1 service provided by Internet Service Provider (ISP)

Component II T1 leased line to ISP Point of Presence (POP)

Component III (2) Cisco routers

Component IV Sun Ultra 1 workstations

Component V Solstice Firewall-1 software

Each of these components will be described in detail in the following pages. A diagram of the system is shown in Figure 1.

Figure 1: Connectivity Architecture for the City of Pittsburgh

3.2.1 COMPONENT I - T1 SERVICE

Description:

The Internet Service Provider will be the interconnection between the City network and the Internet as a whole. The T1 line from the City will terminate at the ISP's Point of Presence (POP), and the ISP will route all outbound traffic from the City to the rest of the Internet, and inbound traffic from the Internet to the City. The ISP will also provide Secondary DNS, backup Mail Exchanger services, a full NNTP USENET News feed, and 24x7 live person technical support for troubleshooting and network operations.

Specific Requirements:
Requirement Description
Comments
1
Accept a full-speed clear channel T1 connection from the City of Pittsburgh
2
Route inbound and outbound TCP/IP packets between the City of Pittsburgh and the Internet, using the City's existing registered netblock of IP addresses

(205.141.128-191)

3
T3 or higher upstream connection, or multiple upstream connections
4
Documentation of upstream and downstream connectivity, so that overcommit percentage can be calculated
5
24x7 Network Operations Center, phone answered by live person
6
No additional charges for technical support, troubleshooting, problem resolution
7
Single point of contact for all connectivity-related issues (ISP handles both their own services and T1-line issues)
8
Documented internal network design to minimize downtime (redundant equipment, backup power supplies, switchover plans, etc.)
9
Provide Secondary DNS service for the City domain name (CITY.PGH.PA.US) and any subdomains
10
Provide a full NNTP USENET News feed
11
Provide backup Mail Exchanger (MX) services for situations when the City's own mail server is out of operation
12
Assist in procurement and management of a domain name for the City (CITY.PGH.PA.US)
13
No restrictions on downstream connections that the City may wish to provide to affiliated or other organizations
14
Supply references to at least two organizations in the Greater Pittsburgh area that currently have T1 or higher connections from this ISP and are willing to discuss the service they have received from the ISP

3.2.2 COMPONENT II - T1 leased line to ISP Point of Presence

Description:

The T1 line interconnects the City's network to the ISP's Point of Presence. This will be a clear-channel T1 circuit (1.544Mbps).



Requirement Description
Comments
1
Full-speed clear channel T1 connection between the City of Pittsburgh and the ISP's Point of Presence
2
Single point of contact for all connectivity-related issues (ISP handles both their own services and T1-line issues)
3
Line Termination Equipment (e.g. CSU/DSU's) with proper interfaces for ISP and City router connections
4
Printed documentation for operation, configuration, programming, etc. of all components, e.g. CSU/DSUs. (CD-ROM based documentation is not sufficient)
5
Minimum 1-year support for all components (e.g. CSU/DSUs), including: hardware troubleshooting, repair, and replacement; no-fee technical support; and all software upgrades, bug fixes, documentation changes, etc. at no charge.

3.2.3 COMPONENT III: - (2) CISCO Routers

Description:

One CISCO router connects the City's internal network to the near side of the firewall, and the other connects the far side of the firewall to the CSU/DSU drivers for the T1 line to the Internet. This configuration provides a very high degree of security and flexibility in implementing security policies.
Requirement Description
Comments
1
exterior screening router has proper interface to connect to CSU/DSU for leased line, and 10BASE-T interface to connect to firewall
2
interior screening router has two 10BASE-T interfaces, one to connect to firewall and one to City internal network.
3
both routers support TCP/IP routing with all major routing protocols. Support for other network protocols (IPX, NETBEUI, AppleTalk, etc.) or WAN interfaces (X.25, etc.) is not required.
4
CISCO IOS software current version
5
sufficient performance in each router to handle wire-speed Ethernet (10Mbps) in and out while applying Access Control Lists (ACL) of some complexity
6
Printed documentation for router operation, configuration, programming, etc. (CD-ROM based documentation is not sufficient)
7
Minimum 1-year support including: hardware troubleshooting, repair, and replacement; no-fee technical support; and all software upgrades, bug fixes, documentation changes, etc. at no charge.

3.2.4 COMPONENT IV: (2) Sun Ultra 1 Workstations

Description:

This is the hardware platform on which the firewall software will run. One computer acts as the Management Station, running the management and logging software. The second computer acts as the Firewall Station, and performs the actual filtering and inspection of packets. The Firewall Station will have separate connections to the City internal network and the T1 link to the Internet. Any traffic passing between these two networks will go through the firewall, which will inspect all traffic and enforce City network security policies. See Figure 2 for an illustration of how the Management and Firewall Stations interact.

In addition, any City Internet servers (World Wide Web, E-mail, FTP, etc.) will be attached to the firewall system via an individual Ethernet connection. Since different sets of rules can be applied to different Ethernet ports, the firewall will be able to enforce the security policies with a sufficient granularity to prevent any interaction between servers in the event that any one of the servers is compromised. See Figure 3 for a representation of how this would be configured. This is a conceptual diagram only, and not meant to represent the specific location of connectors on the rear panel of a Sun Ultra 1/170E.

Figure 2: Firewall and Management Stations

Figure 3: Illustration of Firewall Station Rear Panel

Component IV: (2) Sun Ultra 1 Workstations (continued)
Requirement Description
Comments
Both stations (Firewall & Management):
1
(2) 2.1 GB Internal hard drives
2
128MB RAM
3
Standard TurboGX graphics
4
Internal Quad-speed 644MB SunCD CD-ROM drive
5
Sun 8mm DAT tape drive
6
Sun Internal floppy drive
7
Solaris operating system software License and Media (current version)
8
Standard Sun accessories (keyboard, mouse, mousepad, etc.)
9
Printed documentation for hardware and software (CD-ROM based documentation is not sufficient)
10
Minimum 2-year support including no-fee technical support and all software upgrades, bug fixes, documentation changes, etc. at no charge.
Management station only:
11
Sun Ultra 1 Workstation Model 140
12
Sun 20" color monitor
Firewall station only:
13
Sun Ultra 1 Workstation Model 170E
14
(2) Sun Quad Ethernet SBUS cards
15
Sun 17" color monitor

3.2.5 Component V: - Solstice Firewall-1 Software

Description:

The Firewall-1 software provides a comprehensive platform for implementing security policies and applying them to communications between the City's internal network and the Internet. A fine degree of control can be exercised over the nature and origin of these communications. Firewall-1 retains the performance advantages of packet-filtering gateways, while using Stateful Multi Layer Inspection (SMLI) to transparently achieve application proxy-style control over both stream based (TCP) and datagram (UDP) connections.

Firewall-modules reside on the Firewall station and the Management station. The Firewall station runs those modules that perform the actual interception, inspection, control, and logging of packets, while the Management station runs the GUI used to implement the security policies and analyze and store log file information, The Management station also creates and installs Access Control Lists (ACLs) for the routers in order to provide a consistent implementation of security policy among both the Firewall station and the routers. Firewall-1 has the capability to control multiple firewalls from a single Management station, using a consistent rule base and centralized logging facilities. This provides an ideal expansion path as the City's level of integration with the Internet increases.

Current City plans do not call for the implementation of a Virtual Private Network (VPN) architecture; as a consequence, the Solstice Firewall-1 software in this RFP is not required to contain the VPN/encryption features.

Requirement Description
Comments
1
Solstice Firewall-1 Unlimited Internet Security Center (current version)
2
(2) Solstice Firewall-1 Single Router Security Modules (current version)
3
Printed documentation for all software modules (CD-ROM based documentation is not sufficient)
4
Minimum 2-year support including no-fee technical support and all software upgrades, bug fixes, documentation changes, etc. at no charge.

4.0 RFP RESPONSES:

Responses to this RFP should include the purchase, installation, and configuration of all the required elements described herein. The contract will be awarded to a single entity whose response addresses all the elements of this RFP. That entity will be responsible for the successful implementation of the project, and required to coordinate the efforts of other entities (specified in the response) performing separate pieces of the overall project.

Responses should include one-year support for Components I, II, and III (ISP, T1, routers), and two-year support for Components IV and V (Sun Ultras and Firewall-1). Additional consideration will be given to the proposal that demonstrates a clear and cost-effective upgrade path for moving to connection speeds above T1.

5.0 VENDOR QUALIFICATIONS

The vendor must demonstrate in the written proposal an established base of customers in high speed dedicated Internet Services and must have experience in the installation and implementation of internet services. The vendor must provide a partial listing of existing customers. This listing must include for each customer a name, organization, address, and phone number of a person to contact for a reference as to vendor and application performance.

6.0 INSTALLATION, TRAINING, DELIVERY AND PAYMENT

This analysis, if selected, will be conducted on site at the user's location by qualified vendor personnel. As part of the pre-installation analysis vendor personnel review operations and define technical requirements. Following the pre-installation analysis, vendor personnel will compile and document the results for user approval prior to installation.

6.1 INSTALLATION AND TRAINING SERVICES

The vendor will offer one or more experienced Installation Specialist(s) to travel to the user's location(s) to set up the communication lines, service, test all service functions and train personnel in software operations.

6.2 Documentation Available at Time of Installation

The vendor must provide a complete set of professionally published manuals and other system documentation (including software user's guides and operating system reference manuals) at the time of installation. At least one copy of all documentation must be supplied in hard copy format. CD-ROM or other electronic formats may be used for additional copies beyond the first.

6.3 Delivery and Payment

The vendor must deliver and install a "turn-key" internet service within 90 days after the awarding of the contract. Payment will not be made until the service has been fully implemented and accepted by the City.



6.4 Training

The vendor will make available the following services:


Instructors must display qualifications that demonstrate their ability to meet the requirements of this RFP.

6.5 MAINTENANCE AND CUSTOMER SUPPORT SERVICES

The vendor will make available a consultation service on a toll free or local access line. This service will provide same day response to questions about support regardless of previous training.

7.0 CONTRACTURAL CONDITIONS

7.1 Rights of Assignment

The City Information Systems Office reserves the right to award different portions of the project to different firms if upon review of the proposal it concludes that this would allow more effective and economical completion of the project. The City Information Systems Office is not obligated to accept the lowest-cost proposal.

7.2 Financial Terms and Conditions

The vendor will submit monthly invoices to City Information Systems Office for service and lease line charges, and will be paid in conjunction with City policies and procedures.

7.3 Contractual Terms and Conditions

The contract for this project will be with the City of Pittsburgh and with Vendor and will be administered by the Director of City Information Systems for the Information Systems office. The Director of Information Systems will make the final approval of the appointment of the vendor to this service contract.

7.4 Guarantee of Functionality

The vendor guarantees, by responding to this RFP, an operational system as described in the RFP, the proposal, and any and all representations submitted with, reference by, or provided pursuant to the proposal. This guarantee is not restricted by any other term, condition, disclaimer, warranty, or guarantee.

7.5 Insurance

The City requires vendors to maintain liability insurance, with the City as additional insured. The minimum required coverage is not determined until after the contract is awarded and the final scope of services is settled, but the amounts typically are:

Public Liability		Each		
and Property Damage		Occurrence		Aggregate

Bodily injury, including death	$500,000		$1,000,000
Property damage			$500,000		$  100,000

7.6 Worker's Compensation

The vendor must certify that it has accepted the provision of the Worker's Compensation and Occupational Disease Acts, as amended and supplemented, insofar as the work covered by the contract is concerned, and that it has insured its liability thereunder in accordance with the terms of said Acts or has duly filed a proper certificate of exemption from insurance with the Pennsylvania Department of Labor and Industry.

7.7 Indemnity

The vendor must agree to indemnify, save and hold harmless, and defend the City, its officers, agents and employees against liens, charges, claims, demands, losses, costs, attorney's fees, judgments, liabilities and damages of every kind and nature whatsoever arising by reason of the performance of the third party contractor, its employees, representatives, or against any obligations under the contract.

7.8 Patent Indemnity

The contractor shall indemnify and at all times keep the City indemnified against any action, claim, suit, or demand, costs or expenses arising from or incurred by reason of any infringement of alleged infringement of any patent, design, trademark or name copyright or other protected right, in respect or any materials, goods, articles, services, equipment, machinery, plant or thing, system or method of performing, using, fixing, working or arrangement used or fixed or supplied by the vendor.

7.9 Third Party Liability

Nothing under this agreement shall be construed to grant any rights or interests in this agreement to anyone other than the City and the vendor, and all duties and responsibilities undertaken pursuant to this agreement shall be for the sole and explicit benefit of the City and the contractor and not for the benefit of any other party.

8.0 AFFIRMATIVE ACTION AND ANTI-DISCRIMINATION

8.1 Minority and Women's Business Enterprise Participation

Minority Business Enterprise (MBE) and/or Women Business Enterprise (WBE) participation is requested in all City of Pittsburgh contracts. Such participation may be demonstrated by utilization of MBE/WBE firms through the use of subcontracts with such firms in support services, supplies, etc.

The vendor shall include in the proposal a plan on how and to what extent the MBE/WBE participation will be utilized. Along with the plan, the following documents from Appendix A must be completed and submitted with the proposal:

MBE/WBE Solicitation and Commitment Statement

Bidder's Previous History

MBE/WBE Solicitation and Commitment Statement - Additional information

In order for the proposed MBE/WBE participation to be considered, a copy of a current MBE/WBE certification for the vendor or subcontractor must be submitted with the proposal. Only ceritifications by the City of Pittsburgh, County of Allegheny, Pennsylvania Department of Transportation (PennDot), the Commonwealth of Pennsylvania - Department of General Services, or other recognized government entity will be accepted.

The goals suggested by the City of Pittsburgh for the MBE and/or WBE utilization are 25 percent MBE and 10 percent WBE of the dollar volume of the contract.

8.2 Anti-Discrimination

The vendor must conform with the applicable sections of the Pittsburgh Code: Title Six - Conduct and Article V -Discriminaion.

8.3 Debarment

Vendor will warrant that it is not prohibited from ultimately entering into an Agreement with the City by reason of disqualification under Subsection (b) of Section 161-22 of the Pittsburgh Code. An affidavit certifying compliance with this Section is attached in APPENDIX A and will be incorporated into and made a part of an Agreement.

8.4 Statement of Affiliation

The Vendor shall file a Statement of Affiliations with the City of Pittsburgh Board of Ethics within thirty (30) days of the Execution of an Agreement. The statement of Affiliation shall include:

A) A description of any contractual or other business relationship with the City or any of its department, agencies, boards, commissions or authorities, including the value of the contract or business relationship entered into during the three (3) calendar years previous to the execution of the Agreement.

B) The vendor's qualifications and experience which shall be applied to the performance of the Agreement.

C) An identification of the Contractor's principals, including the names and addresses of all owners or partners or shareholders and officers, or, if the Consultant is a public corporation, the officers, the members of the Board of Directors, and shareholders holding more than three (3) percent of the corporate stock.

The Statement of Affiliations shall be filed in accordance with any rules of procedures established by the Board of Ethics.

9.0 RESPONSE, EVALUATION AND SELECTION PROCEDURES

9.1 Proposal Format and Contents

Proposals should explain Vendor's recommended choice of techniques for each task in Section 3.0 Scope of Services, and the rationale behind his/her choice, and should include in particular the following:

Personnel, their task assignments in this project, and their qualifications, including the professional/instructional qualifications of teaching personnel that demonstrate their ability to fulfill the requirements of this project.

The experience and capabilities of the Vendor in performing projects of this type.

A description of the procedures and topics to be developed and an outline for training ideas.

Complete documentation for the use of software.

Estimated costs (see 9.3)

9.2 Modifications

Where a firm would recommend modifications of changes in the provisional technical or operational specifications, these should be clearly noted.

9.3 Cost Estimates

The cost section of the proposal shall contain the following, clearly identified subsections:

Total Bid Price - the total bid prices for all application services, including but not limited to software, software modifications, training, support, equipment, travel, room, board and supplies and other items needed for the completion of the contract excepting those specifically stated to be the vendor's responsibility in the RFP.

Itemized Costs - itemized costs for each task or service provided must be explicitly stated.

Additional Rates - rates for additional service options that are not part of the contract and the conditions under which they are invoked should be explicitly stated.

Maintenance Contract - the vendor must submit maintenance payment information for hardware for a one (1) year period.

9.4 Vendor Qualifications and Selection Criteria

Firms must be capable of performing and properly completing each of the items specified in this request for proposal. A proposal will not be acceptable from any firm that does not submit complete information on the qualifications and performance of its organization. Information shall include statement setting forth the proposed organization's business and technical program, its financial resources, description of equipment and personnel available for the project, previous experience in software development and training; and other information deemed pertinent to this project.

9.5 Selection Criteria

The firm will be selected on the basis of:

Compliance with the selection criteria and process specified in this section,

The extent to which written proposal addresses items specified in Scope of Services section of this request,Cost and merits of the proposed work program,

Qualifications and capabilities of the vendor and its personnel,

Possibly, an interview (non-reimbursable) with the representative of the firm.

9.6 Selection Procedure

This request for proposals will be advertised in newspapers of general circulation in the Pittsburgh Area on Sunday, June 23, 1996. The RFP will be mailed Friday, June 21,1996 to pre-selected firms known to City Information Systems as offering services in the field of Internet Services.

Firms having questions about the request for proposal may submit them in writing to Howard Stern, Assistant Director, City Information Systems, Public Safety Building, 4th Floor, 100 Grant Street, Pittsburgh, Pennsylvania 15219.

Proposals should be sent by certified mail or any other means that guarantees a signed receipt.

Proposals must be received at City Information Systems Office, City of Pittsburgh, Public Safety Building, 4th Floor, 100 Grant Street, Pittsburgh, PA 15219, by 5:00 p.m., Friday, July 12, 1996.

Each firm shall submit three (3) copies of its proposal.

After initial review and discussion of the proposals, City Information Systems may interview those firms that it selects as finalists.

Any oral interviews with the finalists would be conducted in the City Information Systems office. Firms invited to the oral interview will not be reimbursed for travel, or other costs associated with the visit. Interviews will last not more than one hour, of which the first 15 minutes will be set aside for the firm's presentation and the remainder devoted to questions and discussion.

So that the development and implementation of the internet services may begin quickly, the City Information Systems office will make its final selection and notify the firm selected as soon as possible after the interviews. Notification may be delayed, however, pending enactment of a City Council Resolution authorizing expenditures for this project.

9.7 Selection Schedule

DAY		DATE			TASK

Sunday		June 23, 1996		Project advertised & mailed to known consultants

Friday		July 12, 1996		Deadline for receipt of Proposals, 5:00 p.m.

Friday		July 19, 1996		Short list selected.

		July 19-26, 1996	Interviews of short-listed firms

Friday		July 26, 1996		Proposal negotiations: by telephone

Friday		August 2, 1996		Final selection pending City authorization

9.8 Choice of Features

This RFP is intended to give respondents guidance as to the features and capabilities that the City Information Systems office expects to find necessary or useful in serving its needs. However, the City Information Systems office may at its sole discretion choose to make use of different features and capabilities if the City determines that they would more effectively serves its interests.

  1. Right to Change Process, Schedule, Terms and Conditions, Specifications, Criteria for

Selection and Reject Bids